OPERATIONS

Unocal Indonesia reports ups and downs

Unocal Corp has reported on progress at its operations in deepwater offshore Indonesia; specifically its Gendalo, Gehem-Ranggas and West Seno fields.

Unocal Indonesia reports ups and downs

In the Gendalo field, in the Ganal PSC, Unocal and Eni SpA have agreed upon a development concept for Phase-1 of the project. According to Unocal, “Final engineering design will begin immediately and the plan of development is expected to be submitted to the Indonesian Government later in the year.”

“This first phase will be designed to produce 250 - 300 mmscfd [and] the project is targeted for a 2007 startup depending on government approvals. The project will target existing contract requirements for the Bontang gas market and new sales,” added the firm.

The company’s Gehem discovery, in close proximity to the Ranggas field, has allowed for both fields to make use of a common host facility and plans are afoot for a joint development.

“The company expects to submit a plan of development for the Gehem-Ranggas field in 2005 [and], in support of the joint development, Unocal Ganal Ltd and Unocal Rapak, Ltd, have also completed drilling operations at the Gehem-3 and Ranggas-7 appraisal wells,” said Unocal.

Unocal also revealed it had conducted additional appraisal activity on the Gula structure.

In a statement the firm said, “The Gula-3 well was drilled 3.5 miles south of the Gula-1 discovery well. The well, located in the Ganal PSC area, was drilled in 5,990 feet of water to a total vertical depth of 17,502 feet.”

“This total depth is more than 1,000 feet deeper than was drilled in Gula-1. Gula-3 encountered 327 feet of net gas pay and 6 feet of net oil pay,” it added.

Finally, the West Seno field, which is operated by Unocal unit Unocal Makassar Ltd, has encountered mix results.

“The West Seno field currently has 20 completed wells, with gross production averaging 24,000 BOE per day in June, which is a 7,000 BOE per day increase from April. By year-end 2004, 26 to 28 wells are expected to be online with an expected exit rate (gross) of 25,000 to 35,000 BOE per day,” said Unocal, describing Phase-1 of the development.

“Bids were recently opened for Phase-2 development, including offshore installation and tension leg platform fabrication. The company believes that the bid results were unacceptably high. Accordingly, cost reduction options are being considered, and the construction period is expected to extend beyond 2005,” added the firm, effectively resulting in a delay to Phase-2.

According to Unocal CEO Charles Williamson, “The Company continues to face production problems [at West Seno but] I feel confident about 2005-2006.”

“Although West Seno has not performed up to expectations, this is a significantly positive project,” he added.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry