The Arranoo reservoir appraisal/development well is being drilled directionally from a surface location adjacent to the Dongara-24 and Dongara-34 wells to a target bottom hole location about 640 metres north of the surface location.
The vertical depth to the prognosed top of the primary objective Arranoo Sandstone is 1,387m, (1,596m measured depth). The proposed total depth of the well is 1,850m measured depth, including the main bore and a 160 metre lateral. The well is expected to take 18 days to drill and complete.