CONSTRUCTION of Energexs new $A17.2 million substation at Varsity Lakes on the Gold Coast is on t...

Substation on track for finish line

Site works for the substation and cabling works project, which involves the construction of a new substation, commissioning of two new transformers and new underground electricity cables in the distribution area, began last December.

Ipswich-based company TP Turner is the construction contractor.

The excavation works are well underway and the cable work is expected to be finished at the end of October.

The Varsity Lakes project is part of an $A85 million program to upgrade Energex’s infrastructure in the region. It will provide greater network capacity to residential and commercial customers in Varsity Lakes, Robina, Miami, Burleigh Heads and the Bond University area.

According to latest Energex figures, more than 3000 customers per month joined Energex’s network in 2004.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry