OPERATIONS

Basker-Manta EPT reserves upgraded by a third

A SIX-month extended production test (EPT) at the $A330 million Basker-Manta oil project is now complete, with an independent engineering audit further upgrading reserves 33% to 39.2 million barrels (MMbbl).

Basker-Manta EPT reserves upgraded by a third

In addition to this upgrade, technical consultants, Gaffney Cline and Associates (GCA), provided a certification of the Basker-Manta-Gummy oil, condensate and gas resources.

Since the project began 18 months ago, project operator Anzon said the proved and probable oil reserves have increased nearly 70%, after deducting EPT production.

In delineating this oil and gas resource, the EPT and drilling activity has identified a project expansion to include an integrated oil and gas development, Anzon said.

This development would address 379.2 petajoules of gas and 19.1MMbbl of oil and condensate. This equates to 118 million barrels of oil equivalent (MMboe) of reserves and contingent resources, a 240% jump on the previously reported estimate of 49.3MMboe.

Anzon said the classification of gas and gas liquids as a contingent resource applies only while the gas project awaits the formal commitment to a gas contract and joint venture approval, expected in the next month.

“The many project achievements of this significant development, including its fast track implementation, innovative concept using a mini-FPSO and shuttle tanker, project de-risking and rapid approvals, have been recognised by the international industry as one of the top five offshore projects in 2005,” Anzon said.

The Basker Manta oil development project is now entering its final months, having this week reached a 94% level of completion and with the Crystal Ocean and Basker Spirit undergoing upgrades in Singapore dockyards before returning to begin forecast production of 25,000 barrels of oil per day, anticipated in mid-October.

The project recorded a final capital cost estimate of $330 million, an 8.6% increase on the previously reported estimate.

Meanwhile, the JV is currently finalising the feasibility and conceptual design, as well as securing a market for gas produced from the Basker, Manta and Gummy fields.

Current estimates are to produce at least 50-60 terajoules per day starting in January 2008, with an accelerated development to deliver gas to the Eastern Gas Pipeline near Orbost in East Gippsland.

Anzon and Beach Petroleum each hold a 50% stake in the Basker-Manta-Gummy project.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry