Po fast-tracks Vitalba gas project

FOLLOWING its successful listing on the Australian Stock Exchange last week, Po Valley Energy has...

Po Valley has begun civil works on Vitalba and these works should take about 4-6 weeks depending on weather conditions, according to the company.

The drill rig is expected to mobilize to the Vitalba-1 drill site in early February 2005.

Vitalba has proven and probable reserves of 8.6 bcf and has previously produced 12.6 bcf of gas from one production well under the management of ENI, according to Po Valley CEO Michael Masterman.

“Vitalba is the first cab off the rank and should be shortly followed by Sillaro – its a good early start to the 2005 development program,” Masterman said.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry