Moomba at full gas production ahead of schedule

Santos has said full gas processing capacity has been achieved - ahead of schedule - from the Moomba plant, which was damaged by fire on New Year’s Day.

Moomba at full gas production ahead of schedule

A Santos statement said total Moomba gas production capacity has now achieved levels of approximately 630 terajoules per day - which equates with pre-incident capability - as a result of the resumption of processing through the Liquids Recovery Plant B train in Dew Point Control Mode.

It said it was an important milestone for the Moomba recovery project and will enable the plant to meet the coming winter peak gas demand.

Further repair work remains on schedule to fully restore natural gas liquids production with the Liquids Recovery Plant A train start-up scheduled for the first half of May and Liquids Recovery Plant B train start-up scheduled for the second half of July.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry