Pluto pushed back to August

WOODSIDE Petroleum has announced an expected delay in the start-up of its Pluto liquefied natural gas project by six months to August 2011, with costs increasing by 6.9% to $14 billion.

Pluto pushed back to August

The company said the delay was due to the failure of the project's flare tower contractor to take into account the specified wind loading requirement of the flare towers. Woodside added it had chosen...

Start a free trial to continue reading this article

Already have an account?

Subscribe now

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry