BassGas to reach full production in late July: Origin

THE jinxed BassGas project now almost two years behind its original schedule is expected to fin...

This article is 18 years old. Images might not display.

The offshore Otway Basin project’s problems are the subject of a claim and counter-claims for damages between operator Origin Energy and the original engineering, procurement, installation and commissioning contractor Clough.

BassGas began producing gas in May and condensate in June. But Origin spokesman Angus Guthrie said the commissioning phase was near its end.

Work was also continuing on the source Yolla A platform.

BassGas has estimated reserves of 307 billion cubic feet of gas, 14 million barrels of condensate and 800,000 bbl of oil. It is expected to supply about 10% of Victoria’s energy needs for the next 15 years.

The BassGas joint venture comprises Origin Energy (operator and 42.5% equity), Australian Worldwide Exploration (30%), CalEnergy (15%) and Mitsui subsidiary Wandoo Petroleum (12.5%).

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

Future of Energy Report: Nuclear Power in Australia 2024

Energy News Bulletin’s new report examines what the energy and resources industry thinks of the idea of a nuclear-powered Australia.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.