GAS

Pohokura glitches won't delay first gas: Shell

MAJOR technical hitches, including instability of the seabed at the offshore development well sit...

This article is 18 years old. Images might not display.

But operator Shell Exploration New Zealand says the aspects of the project that are critical to gas delivery remain on schedule, with first gas from the 750 petajoule field still expected later this year.

The jack-up Ensco Rig 56 has been sitting off the Motunui coast since mid-March, unable so far to start drilling the planned six offshore developments wells.

As a result, other specialised equipment is lying idle after being delivered to Taranaki weeks ago to meet planned engineering and construction schedules.

This includes the heavy-lift ship Annegret, which has been forced to remain tied up at Port Taranaki since early March, after arriving from Western Australia with the 415-tonne jacket aboard.

In recent days, rumours have been circulating in the Taranaki energy industry that the Pohokura project team and the Ensco rig have struck problems preparing the seabed foundations on which the Pohokura jacket and 165-tonne topsides module will sit.

It is understood the geology of the seabed is presently preventing the securing of the jacket in position and the subsequent drilling, from the platform, by the Ensco rig.

International experts have been called in to solve the seabed problems, but it is not known what solutions are being considered.

There are also rumours that if the matter is not resolved soon, then drilling may be further delayed to avoid any wild winter weather and only resume in the spring.

Shell Exploration NZ has declined to comment on the matter apart from issuing a brief statement cleared by Royal Dutch Shell in The Hague.

“Onshore activity is on schedule and we have completed the wells, which will initially supply gas from the field.

“The offshore portion of the project is currently underway, following a delay to the installation of the platform and adverse weather conditions.

“Overall, the aspects of the project that are critical to gas delivery are on schedule and we continue to expect first gas in 2006,” the company said.

Ironically, calm weather this week has allowed other parts of the offshore development project to proceed, with the multi-purpose offshore support vessel Rockwater-2 moving closer to the Motunui shore to continue laying the flexible pipeline that will eventually carry gas from the platform to the onshore production station for processing.

The Ensign International Rig 41 has now finished drilling the three deviated onshore-offshore production wells and one water-disposal well, allowing the Pohokura partners to start producing and selling some commercial gas from late this year.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

Energy News Bulletin Future of Energy Report 2024

With the global energy market in constant development, this report captures the sentiment of key industry players on the future of energy in Australia – and how it has changed through 2024.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.