EXPLORATION

Chevron Gorgon CCS burns A$25 million hole in supermajor's pocket

FOI shows facility only running at 50% capacity with "de-sanding" issues ongoing

File photo: satellite imagery of Gorgon's CCS facility

File photo: satellite imagery of Gorgon's CCS facility

Under the FOI release, the government was pushed to make public an internal report Chevron commissioned outlining an annual update on its CCS project alone. 

It shows that the project has stored 2.26 million tonnes of CO2 during the 2020-2021 financial year; despite the facility having a nameplate capacity of 4 million tonnes, spread across nine wells. It also noted some reservoir pressure decline. 

Chevron has also revealed operational expenditure on its CSS project: A$13.2 million on "reservoir management," A$2.4 million on maintenance and A$3.2 million on wells maintenance. Labour cost a further A$5.6 million.

The documents also show that the budget for the project has been revised upward from A$3.092 million to A$3.147 million. 

Including other operational expenditure, it brings Chevron's total spend on the project to A$25.6 million. It must pay more than half of this to make up for a payment arrangement of A$40 million to the WA government following its failure to sequester as much CO2 as originally claimed in initial project documentation. 

"In late 2020, the (WA) Department of Mines, Industry Regulation and Safety (DMIRS) imposed an injection limit on the Asset which reduced the injection rate to 70 MMscfd due to issues with starting up the pressure management sites. This was initially flagged in the 2020 annual report," Chevron wrote. 

The project ran at nameplate for the first half of the reporting period, it said. 

"During the first half of the reporting period, injection rates matched the CO2 volume extracted from the feed gas, essentially meeting its functional objective." 

The report was issued to the department of industry, science, energy and resources on Thursday September 30 2021.  

In its report, Chevron notes that it is still determining whether to make public monitoring data for the CSS project, further claiming "it's likely that appropriate data submitted to the Western Australian department of mines...may be made available to the public."  

The CCS facility was shut down for a six week period through 2021 due to maintenance.

Chevron also states on page three of its internal report that "a de-sanding project was initiated to remediate the issue through an upgrade of the surface facilities to remove sand from the process stream." 

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry