EXPLORATION

Santos gets ball rolling on Barrossa

Just a day after Van Gogh announcement

 Barossa-field.jpg

Barossa-field.jpg

 

The gas-condensate field is in production license NT/RL5 about 300km off the coast of Darwin in Northern Australia. 

"These are the final major facilities contracts for Barossa as we get closer to pushing the button on the project's development in the second quarter," Gallagher said.

The contract for the transport and installation of the subsea umbilicals, risers and flowlines as well as the supply of the in-field flowlines, has been awarded to Subsea 7.

Aker Solutions also won contracts for the supply of umbilicals, and National Oilwell Varco Denmark I/S will supply flexible risers.

It follows the award of the FPSO to Modec in October last year. It will be Modec's largest gas FPSO to date.

The facility will dehydrate gas and remove carbon dioxide aboard, before it is transported by an export pipeline onshore for processing.

Condensate produced will be exported directly from the FPSO.

Santos currently holds a 25% stake in Barossa alongside ConocoPhillips (37.5%) and SK Migas (37.5%). Santos also holds an 11.5% interest in the Darwin LNG plant.  

In October last year, the same month it announced the award of the FPSO contract to Modec, Santos revealed it would acquire Conoco's northern Australia and Timor Leste assets.

This will bring the company's stake in Barossa to 62.5% once the transaction closes. However Santos is looking to sell down its stake to between 40% and 50%.

The Barossa field will produce 3.7 million tonnes of LNG and 1.5 million barrels of condensate per year. The field has a lifespan of 25 years.

The award of the final major Barossa contracts comes just a day after Santos announced a final investment decision on the Van Gogh Phase Two oil project.

Santos has a controlling 52.5% interest in Van Gogh alongside Inpex (47.5%).

The Van Gogh field is one of three subsea oil field developments located in the Exmouth Basin, offshore Western Australia, which tie into the Ningaloo Vision FPSO.

First oil from the second phase is targeted for late 2021.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry