OPERATOR Austral Pacific Energy and its PEP 38738 partners have struck trouble again with their o...

Second sidetrack for Cardiff-2

Austral last night told the NZX that the Cardiff-2B deviation well was being kicked off after the first sidetrack Cardiff-2A had encountered good hydrocarbon indications within the upper part of the Eocene-aged Kapuni Formation.

However, unspecified drilling problems led to the plugging back from 4072m and deviating out of that wellbore at 3950m. Austral anticipated Cardiff-2B would reach its target depth near 4900m later in February and would be completed for testing.

Earlier this year operational problems associated with the cementing of a 7” liner across the open hole section of Cardiff-2 led to the first sidetrack, after good quality logs indicated the hydrocarbon-bearing McKee, K1A, K2 and deeper K3E had been intersected.

Austral also said the first jet pump test of the Miocene-aged Mt Messenger pay zone within the nearby Cheal-A4 well had resulted in a total of approximately 3000 barrels of oil and 1.5 mmscf of gas flowing over a 10-day period.

A second test had started, using a larger jet pump nozzle, and during the first three days the well had averaged rates approximately 40% higher than during the first test. Once the second test was finished, a third nozzle would be evaluated and testing conducted over the shallower Urenui oil pay, before both zones were tested together.

A similar testing program would then be conducted on Cheal-A3X, which previously flowed unassisted at rates averaging 300 bopd.

Austral also said it had entered into a formal agreement with UK company Rift Oil Plc whereby Rift would contribute the first US$6 million of expenditure on the Douglas-1 exploration well in Papua New Guinea licence PPL 235 in return for earning a 65% interest in the permit.

"We are delighted to have finalised this agreement, which ensures the drilling of the highly prospective Douglas-1 well this year,” said Austral CEO Dave Bennett.

The Douglas Prospect, mapped as covering 60 sqkm, was situated in a lightly explored area of the foreland basin, where earlier wells had demonstrated oil and gas generation.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.

editions

ENB Cost Report 2021

This industry-wide report aims to understand current cost levels across the energy industry