NEW South Wales gas player Metgasco has had a win in its Supreme Court challenge of the NSW gover...

Delivering the judgment this morning, Justice Richard Button said as the state government's move was not made according to law it should be overturned. He ordered costs be paid to Metgasco.

The company said it would review the Supreme Court's decision in detail before providing a detailed response, but previously indicated it would seek damages over the Office of Coal Seam Gas' decision to revoke its drilling permit in the face of widespread public protests while the Titan Energy Services contracted rig was on the road to the drillsite.

The damages claim could exceed $10 million.

Metgasco says it has spent $120 million over 10 years successfully drilling more than 50 wells to define its CSG resource in the Clarence Moreton Basin, as well as a significant conventional and tight gas potential in the Greater Mackeller structure.

The company secured environmental approval in early 2013 to drill the Rosella-1 well and follow-up on promising results from the Kingfisher-1 discovery well.

Metgasco says it conducted a community consultation program specific to the well, but just weeks after approving the environmental plan the OCSG suspended the approval to drill on the basis that the company failed to comply with NSW government community consultation guidelines - despite not previously expressing any concerns.

Metgasco had secured a drilling location on the land of a farmer who supported the planned well; however, around 2000 protestors moved in amid concerns about the impact of CSG drilling.

Metgasco claimed the OCSG acted in bad faith and asked for the decision be reviewed by an independent party.

It said the government did not have the right to take such action under the Petroleum Onshore Act and that the OCSG had not followed its procedures.

The OCSG and NSW government declined to review their decision. Metgasco began Supreme Court proceedings in June last year, culminating in this morning's decision.

Metgasco says that it has widespread support for the development of the Casino CSG field in the nearby towns of Casino and Grafton, and that coastal communities will not be affected by its operations.

Metgasco has been contacted for comment.

The NSW government is yet to respond to the decision.

Metgasco shares halved from $0.088 when drilling was halted, and recovered 16% to $0.065 in trade this morning.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

Energy News Bulletin Future of Energy Report 2024

With the global energy market in constant development, this report captures the sentiment of key industry players on the future of energy in Australia – and how it has changed through 2024.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.