Court sides with QCLNG

BRISBANE'S Supreme Court has dismissed McConnell Dowell Constructors' attempt to seek damages rel...

This article is 10 years old. Images might not display.

According to The Gladstone Observer, the contractor claimed it was ready to begin works for the $A730 million contract on February 23, 2011 but was prevented from going ahead until June 12, 2011.

The contractor reportedly argued this delay was caused by QCLNG not receiving the required environmental approvals.

It consequently sought compensation from the CSG to LNG joint venture for this period over costs associated with an idle workforce and equipment.

"However, the Brisbane Supreme Court found there were many other factors at play which resulted in QCLNG suspending work and concluded those factors reduced the chances of McConnell Dowell Constructors being able to appeal the decision based on points of law," the newspaper reported.

TOPICS:

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

A growing series of reports, each focused on a key discussion point for the energy sector, brought to you by the Energy News Bulletin Intelligence team.

editions

Energy News Bulletin Future of Energy Report 2024

With the global energy market in constant development, this report captures the sentiment of key industry players on the future of energy in Australia – and how it has changed through 2024.

editions

ENB CCS Report 2024

ENB’s CCS Report 2024 finds that CCS could be the much-needed magic bullet for Australia’s decarbonisation drive

editions

ENB Cost Report 2023

ENB’s latest Cost Report findings provide optimism as investments in oil and gas, as well as new energy rise.

editions

ENB Future of Energy Report 2023

ENB’s inaugural Future of Energy Report details the industry outlook on the medium-to-long-term future for the sector in the Asia Pacific region.